Southern California Culver City 7th Tower Renovations
Renovation of 4,200 SF area at the tower building for hospital staff offices and conference rooms. The scope includes, selective demolition, install new wall, floor, and ceiling finishes, install light fixtures, and install new doors.
Taper ES ADA
Renovation and ADA upgrades across the campus at Taper Elementary School. Scope included upgrades of the paths of travel, drainage, lunch shelter, fire alarm, restrooms, casework, doors and hardware, signage, drinking fountains, and auditorium seats to comply with ADA accessibility requirements.
Kennedy ADA
Renovation of various buildings of the school including classroom building, multipurpose room, parent center, and admin building to accommodate ADA accessibility. Scope includes complete renovation of toilet rooms from structural modification/framing, add seating for ADA accessibility at multipurpose building, modify existing rooms and offices for new layouts/clearances, and add ramps/stairs/handrails to make ADA compatible at […]
Kennedy Elevator ADA
Installation of an ADA modular passenger elevator tying into the classroom building via pedestrian bridge. Scope includes, remove concrete planters/landscape and regrade area for elevator and elevator machine room, new concrete piles with welded structural columns, add exterior skin and roof at elevator and elevator machine room, new transformer for power, and tie in fire […]
Ted Craig Regional Park ReRoof and Refurbish Restrooms
Design-build project for the roof replacement and refurbishment of restroom facilities. Scope included demolition and installation of new roof, interior walls, tile floors, electrical panels, transformers, plumbing fixtures, and doors , door frames, and hardware.
Rework JAMF Security Fence
Installation of 3,200SF of chain link fence in a high security Jail Facility. Scope included installation of 280LF concrete retaining wall with soil nails, installation of new underground electrical conduits, re-grading for new swales and drainage, and installation of new AC paving and concrete slab on grade.
Lompoc Roofing
The FCC Lompoc was constructed in 1946 of cast in place concrete. MIK performed the complete tear off and installation of new APP modified bituminous membrane roofing system on the Housing Units, Administration, Intel Room IR, Visitor VR, Medical Service, and Control CL. Scope included the reinstallation of mechanical equipment, gas piping, surveillance cameras and […]
Replace Cold Water Supply PH444
Replace approximately 750 linear feet of existing galvanized cold water piping with new copper piping and fittings due to deterioration of the existing piping over the years. Scope includes design of new plumbing system, removal and installation of new copper pipe, and drywall repair at walls/ceilings.
VCMC Fainer Improvements
The construction package included multiple OSHPD renovation projects. The individual projects include, 1) removal and replacement of waste, storm, and vent piping, 2) repair existing shaftwall assembly at linen chute shaft on second, third, fourth floors and repair discharge door at first floor, 3) maintenance work to replace casework and associated plumbing fixtures at nurse […]